INITIAL WORKS
The initial works will concern the demolition of Pavilions 7 and 8 to make way for the construction of the new Padiglione Zero and the new Technology Centre.
On 23 October 2023, the site areas affecting St. Jerome’s Abbey (Abbazia di San Gerolamo) and the Technology Centre were handed over to the contractors.
The relocations affect:
- Villa Quartara, where the Training Centre and nursing school were located;
- St. Jerome’s Abbey, where the Emergency Management Operations Centre, maintenance staff offices, laundry, workshop and the men’s changing rooms will be located;
- Pavilion 17, where the women’s changing rooms will be located;
- Pavilion 12, where doctors’ offices will be located on the third floor (for coworking);
- Pavilion 10, where the budget offices will be located on the fourth floor;
- Pavilion 13, used to house the rare diseases centre, social workers and CABEF (an environmental conservation organisation);
- Pavilion 10, where the International Office will be temporarily located on the fourth floor.
Once the relocations have been completed, the controlled demolition of Pavilions 7 and 8 will begin.